Biography of Thermal Evaporator-Cr/Au
AU & SO Details
Authorized Users till date: 393 |
---|
System Owners till date: 10 |
Names of all System Owners
Akash Nigam, Jayashree Ravindranathan, Amit Ranshevare, Vivek Surana, kavita kharad, Anjum Khan, Sharanya Sasidharan, Minita Surwade (NH), Shilpa Kharat, Shahiroze Khetani |
Reservation Details
Year | No. of Bookings | Usage (in hrs.) | Tool blocked (in hrs.) |
---|---|---|---|
2013 | 399 | 753 | 677 |
2014 | 509 | 936.5 | 380 |
2015 | 443 | 869 | 796.5 |
2016 | 624 | 1099.5 | 306 |
2017 | 382 | 762 | 688.5 |
2018 | 239 | 537.25 | 451.75 |
2019 | 144 | 397 | 524 |
2020 | 32 | 84.75 | 233.25 |
2021 | 52 | 179.5 | 212.25 |
2022 | 89 | 273.75 | 338 |
2023 | 99 | 275.75 | 760.5 |
2024 | 33 | 107.5 | 4.25 |
Total bookings:
3045
Total hours: 6275.5
Total hours of blackout: 5372
Complaint Details
Year | No. of Complaints | Complaints Resolved | Downtime(In days) |
---|---|---|---|
2015 | 14 | 14 | 214 |
2016 | 4 | 4 | 5 |
2017 | 15 | 15 | 87 |
2018 | 13 | 13 | 23 |
2019 | 4 | 4 | 20 |
Total Downtime: 349
AMC Details
AMC Taken (Duration: 15-02-2016 to 14-02-2017) |
Cost: 0 |
Work Done : 1st PM done by EMT |
|
Report Submitted: ✓ |
Work Done : 2nd PM done by EMT |
|
Report Submitted: ✓ |
AMC Taken (Duration: 15-02-2017 to 14-02-2018) |
Cost: 0 |
Work Done : 1st PM current year 2017 |
|
Report Submitted: ✓ |
Work Done : 2nd PM current year 2017 |
|
Report Submitted: ✓ |
AMC Taken (Duration: 15-02-2018 to 14-02-2019) No Data Found |
AMC Taken (Duration: 15-02-2019 to 14-02-2020) |
Cost: 0 |
Work Done : PM visit done |
|
Report Submitted: ✓ |
0 |
Work Done : PM Visit Done |
|
Report Submitted: ✓ |
0 |
AMC Taken (Duration: 01-10-2023 to 30-09-2024) No Data Found |