Authorized Users till date: 46 |
---|
System Owners till date: 10 |
Names of all System Owners
Neeraj Panwar, Neha Raorane, Kumari Manisha, Manisha Bansode, SENTHILKUMAR R, Rowtu Srinu (H), Santosh Kumar Yadav, Pijush Chakraborty, Sana Ayyuby, Madhuri Mishra |
Reservation Details
Year | No. of Bookings | Usage (in hrs.) | Tool blocked (in hrs.) |
---|---|---|---|
2013 | 84 | 1024 | 209 |
2014 | 35 | 2470 | 855.5 |
2015 | 44 | 3053.5 | 924.5 |
2016 | 40 | 1863 | 301 |
2017 | 111 | 2585 | 302 |
2018 | 187 | 451.5 | 306 |
2019 | 243 | 704.5 | 140 |
2020 | 41 | 132.5 | 280 |
2021 | 85 | 281.5 | 1330 |
2022 | 190 | 572.5 | 185.5 |
2023 | 151 | 469.5 | 369.5 |
2024 | 78 | 562.5 | 205 |
Total bookings:
1289
Total hours: 14170
Total hours of blackout: 5408
Complaint Details
Year | No. of Complaints | Complaints Resolved | Downtime(In days) |
---|---|---|---|
2015 | 2 | 2 | 10 |
2016 | 1 | 1 | 31 |
2017 | 1 | 1 | 7 |
2018 | 1 | 1 | 12 |
2023 | 2 | 1 | 6 |
Total Downtime: 66
AMC Details
AMC Taken (Duration: 07-01-2015 to 06-01-2016) |
Cost: 0 |
Work Done : PM visit done as per plan |
|
Report Submitted: ✓ |
0 |
Work Done : 2nd PM visit done as per plan |
|
Report Submitted: ✓ |
Work Done : PM visit done as per plan |
|
Report Submitted: ✓ |
AMC Taken (Duration: 15-02-2017 to 14-02-2018) |
Cost: 0 |
Work Done : 1st PM current year 2017 |
|
Report Submitted: ✓ |
AMC Taken (Duration: 15-02-2018 to 14-02-2019) |
Cost: 0 |
Work Done : Old laser fan not working issue solved by Laser science engineer. |
|
Report Submitted: ✓ |
0 |
Work Done : Break Down visit |
|
Report Submitted: ✓ |
Work Done : PLD 1 PM has done |
|
Report Submitted: ✓ |
0 |
AMC Taken (Duration: 15-02-2019 to 14-02-2020) No Data Found |